Auto calculate tasks in MS Project












0















I have two tasks, named Task 1 and Task 2.



Task 2 has two dependancies:




  1. it must start on a specific date (later than the start of Task 1)


  2. it must finish at the exact time of Task's 1 finish FF



I created these dependancies without any problem, wrote them in Predecessors column, but the problem is that the duration of Task 1 may vary, so when i am changind it's duration, Task 2 is not keeping both of the dependancies, only the FF one. Even in the Advanced tab of this task i wrote must start on a specific date.
I managed to to something, inserted another task between these two, let's call it Task 3.



I deleted any dependencies of Task 2, set it to auto schedule and then gave it two dependencies. Task 1 "FF" and Task 3 "SS". Problem is that when i am changing the duration of Task 1, Task 2 is still not auto calculating it's own duration and sticks with the FF function only. But if i click on the Predecessors column and then respect links, it's working. Anyhow, i have have multiple tasks like Task 2 along the project so it's uncomfortable to insert so many Task 3 workarounds ...



So, here is what i need from this task:
To keep the specified start date, to keep the FF dependency and automatically calculate it's duration if i will change the Task 1 dates.
Any help?










share|improve this question





























    0















    I have two tasks, named Task 1 and Task 2.



    Task 2 has two dependancies:




    1. it must start on a specific date (later than the start of Task 1)


    2. it must finish at the exact time of Task's 1 finish FF



    I created these dependancies without any problem, wrote them in Predecessors column, but the problem is that the duration of Task 1 may vary, so when i am changind it's duration, Task 2 is not keeping both of the dependancies, only the FF one. Even in the Advanced tab of this task i wrote must start on a specific date.
    I managed to to something, inserted another task between these two, let's call it Task 3.



    I deleted any dependencies of Task 2, set it to auto schedule and then gave it two dependencies. Task 1 "FF" and Task 3 "SS". Problem is that when i am changing the duration of Task 1, Task 2 is still not auto calculating it's own duration and sticks with the FF function only. But if i click on the Predecessors column and then respect links, it's working. Anyhow, i have have multiple tasks like Task 2 along the project so it's uncomfortable to insert so many Task 3 workarounds ...



    So, here is what i need from this task:
    To keep the specified start date, to keep the FF dependency and automatically calculate it's duration if i will change the Task 1 dates.
    Any help?










    share|improve this question



























      0












      0








      0








      I have two tasks, named Task 1 and Task 2.



      Task 2 has two dependancies:




      1. it must start on a specific date (later than the start of Task 1)


      2. it must finish at the exact time of Task's 1 finish FF



      I created these dependancies without any problem, wrote them in Predecessors column, but the problem is that the duration of Task 1 may vary, so when i am changind it's duration, Task 2 is not keeping both of the dependancies, only the FF one. Even in the Advanced tab of this task i wrote must start on a specific date.
      I managed to to something, inserted another task between these two, let's call it Task 3.



      I deleted any dependencies of Task 2, set it to auto schedule and then gave it two dependencies. Task 1 "FF" and Task 3 "SS". Problem is that when i am changing the duration of Task 1, Task 2 is still not auto calculating it's own duration and sticks with the FF function only. But if i click on the Predecessors column and then respect links, it's working. Anyhow, i have have multiple tasks like Task 2 along the project so it's uncomfortable to insert so many Task 3 workarounds ...



      So, here is what i need from this task:
      To keep the specified start date, to keep the FF dependency and automatically calculate it's duration if i will change the Task 1 dates.
      Any help?










      share|improve this question
















      I have two tasks, named Task 1 and Task 2.



      Task 2 has two dependancies:




      1. it must start on a specific date (later than the start of Task 1)


      2. it must finish at the exact time of Task's 1 finish FF



      I created these dependancies without any problem, wrote them in Predecessors column, but the problem is that the duration of Task 1 may vary, so when i am changind it's duration, Task 2 is not keeping both of the dependancies, only the FF one. Even in the Advanced tab of this task i wrote must start on a specific date.
      I managed to to something, inserted another task between these two, let's call it Task 3.



      I deleted any dependencies of Task 2, set it to auto schedule and then gave it two dependencies. Task 1 "FF" and Task 3 "SS". Problem is that when i am changing the duration of Task 1, Task 2 is still not auto calculating it's own duration and sticks with the FF function only. But if i click on the Predecessors column and then respect links, it's working. Anyhow, i have have multiple tasks like Task 2 along the project so it's uncomfortable to insert so many Task 3 workarounds ...



      So, here is what i need from this task:
      To keep the specified start date, to keep the FF dependency and automatically calculate it's duration if i will change the Task 1 dates.
      Any help?







      microsoft-project






      share|improve this question















      share|improve this question













      share|improve this question




      share|improve this question








      edited Jul 1 '14 at 8:44









      Jens Erat

      12.9k114660




      12.9k114660










      asked Jul 1 '14 at 8:12









      i5sec0ndzi5sec0ndz

      114




      114






















          1 Answer
          1






          active

          oldest

          votes


















          0














          Ok, here's what to do:




          1. On the Advanced tab set the Task Type of Task 2 to be "Fixed Work"


          2. Link Task 2 to Task 1 with a Start-to-Start dependancy (include some lag if you wish to start it a fixed amount after Task 1 starts)


          3. Go to the cell containing the Finish Date of Task 1 and Ctrl-C it to copy the date into the cut buffer


          4. Go to the cell containing the Finish Date of Task 2. Right click, Paste Special and select Paste Link



          You will now find that as Task 1 changes duration, Task 2 will also change duration to match it, and will always start on the designated start date (plus any lag you added)






          share|improve this answer
























            Your Answer








            StackExchange.ready(function() {
            var channelOptions = {
            tags: "".split(" "),
            id: "3"
            };
            initTagRenderer("".split(" "), "".split(" "), channelOptions);

            StackExchange.using("externalEditor", function() {
            // Have to fire editor after snippets, if snippets enabled
            if (StackExchange.settings.snippets.snippetsEnabled) {
            StackExchange.using("snippets", function() {
            createEditor();
            });
            }
            else {
            createEditor();
            }
            });

            function createEditor() {
            StackExchange.prepareEditor({
            heartbeatType: 'answer',
            autoActivateHeartbeat: false,
            convertImagesToLinks: true,
            noModals: true,
            showLowRepImageUploadWarning: true,
            reputationToPostImages: 10,
            bindNavPrevention: true,
            postfix: "",
            imageUploader: {
            brandingHtml: "Powered by u003ca class="icon-imgur-white" href="https://imgur.com/"u003eu003c/au003e",
            contentPolicyHtml: "User contributions licensed under u003ca href="https://creativecommons.org/licenses/by-sa/3.0/"u003ecc by-sa 3.0 with attribution requiredu003c/au003e u003ca href="https://stackoverflow.com/legal/content-policy"u003e(content policy)u003c/au003e",
            allowUrls: true
            },
            onDemand: true,
            discardSelector: ".discard-answer"
            ,immediatelyShowMarkdownHelp:true
            });


            }
            });














            draft saved

            draft discarded


















            StackExchange.ready(
            function () {
            StackExchange.openid.initPostLogin('.new-post-login', 'https%3a%2f%2fsuperuser.com%2fquestions%2f775419%2fauto-calculate-tasks-in-ms-project%23new-answer', 'question_page');
            }
            );

            Post as a guest















            Required, but never shown

























            1 Answer
            1






            active

            oldest

            votes








            1 Answer
            1






            active

            oldest

            votes









            active

            oldest

            votes






            active

            oldest

            votes









            0














            Ok, here's what to do:




            1. On the Advanced tab set the Task Type of Task 2 to be "Fixed Work"


            2. Link Task 2 to Task 1 with a Start-to-Start dependancy (include some lag if you wish to start it a fixed amount after Task 1 starts)


            3. Go to the cell containing the Finish Date of Task 1 and Ctrl-C it to copy the date into the cut buffer


            4. Go to the cell containing the Finish Date of Task 2. Right click, Paste Special and select Paste Link



            You will now find that as Task 1 changes duration, Task 2 will also change duration to match it, and will always start on the designated start date (plus any lag you added)






            share|improve this answer




























              0














              Ok, here's what to do:




              1. On the Advanced tab set the Task Type of Task 2 to be "Fixed Work"


              2. Link Task 2 to Task 1 with a Start-to-Start dependancy (include some lag if you wish to start it a fixed amount after Task 1 starts)


              3. Go to the cell containing the Finish Date of Task 1 and Ctrl-C it to copy the date into the cut buffer


              4. Go to the cell containing the Finish Date of Task 2. Right click, Paste Special and select Paste Link



              You will now find that as Task 1 changes duration, Task 2 will also change duration to match it, and will always start on the designated start date (plus any lag you added)






              share|improve this answer


























                0












                0








                0







                Ok, here's what to do:




                1. On the Advanced tab set the Task Type of Task 2 to be "Fixed Work"


                2. Link Task 2 to Task 1 with a Start-to-Start dependancy (include some lag if you wish to start it a fixed amount after Task 1 starts)


                3. Go to the cell containing the Finish Date of Task 1 and Ctrl-C it to copy the date into the cut buffer


                4. Go to the cell containing the Finish Date of Task 2. Right click, Paste Special and select Paste Link



                You will now find that as Task 1 changes duration, Task 2 will also change duration to match it, and will always start on the designated start date (plus any lag you added)






                share|improve this answer













                Ok, here's what to do:




                1. On the Advanced tab set the Task Type of Task 2 to be "Fixed Work"


                2. Link Task 2 to Task 1 with a Start-to-Start dependancy (include some lag if you wish to start it a fixed amount after Task 1 starts)


                3. Go to the cell containing the Finish Date of Task 1 and Ctrl-C it to copy the date into the cut buffer


                4. Go to the cell containing the Finish Date of Task 2. Right click, Paste Special and select Paste Link



                You will now find that as Task 1 changes duration, Task 2 will also change duration to match it, and will always start on the designated start date (plus any lag you added)







                share|improve this answer












                share|improve this answer



                share|improve this answer










                answered Jul 8 '14 at 14:10









                Marv MillsMarv Mills

                1816




                1816






























                    draft saved

                    draft discarded




















































                    Thanks for contributing an answer to Super User!


                    • Please be sure to answer the question. Provide details and share your research!

                    But avoid



                    • Asking for help, clarification, or responding to other answers.

                    • Making statements based on opinion; back them up with references or personal experience.


                    To learn more, see our tips on writing great answers.




                    draft saved


                    draft discarded














                    StackExchange.ready(
                    function () {
                    StackExchange.openid.initPostLogin('.new-post-login', 'https%3a%2f%2fsuperuser.com%2fquestions%2f775419%2fauto-calculate-tasks-in-ms-project%23new-answer', 'question_page');
                    }
                    );

                    Post as a guest















                    Required, but never shown





















































                    Required, but never shown














                    Required, but never shown












                    Required, but never shown







                    Required, but never shown

































                    Required, but never shown














                    Required, but never shown












                    Required, but never shown







                    Required, but never shown







                    Popular posts from this blog

                    "Incorrect syntax near the keyword 'ON'. (on update cascade, on delete cascade,)

                    Alcedinidae

                    Origin of the phrase “under your belt”?